A masonry hall built to the enclosed shell stage most often costs 2,800 PLN/m² (typically 2,800 ‑ 3,650 PLN/m²), while a steel hall clad with sandwich panels costs 2,400 PLN/m² (typically 1,800 ‑ 2,550 PLN/m²). A steel hall is therefore usually cheaper and quicker to build, while a masonry hall is more durable and retains heat better.
At a glance (as at 5 October 2026)
- A masonry hall built to the enclosed shell stage usually costs 2,800 ‑ 3,650 PLN/m².
- A steel hall with sandwich-panel cladding and installation usually costs 1,800 ‑ 2,550 PLN/m².
- At the median rate, a 500 m² masonry hall costs about PLN 1,400,000 for an enclosed shell, while a steel hall costs about PLN 1,200,000.
- Based on a price-list example, a turnkey 500 m² steel hall costs about PLN 650,000.
- The medians are based on 3 sources for masonry halls and 3 for steel halls, collected by indekscen.pl.

A hall is usually a business investment: a warehouse, workshop, production facility or outbuilding on a plot of land. The first question is generally the same: steel or masonry? We compare medians from public articles and contractors’ price lists, calculate examples for halls of 100, 300 and 500 m², and explain what the price per metre excludes, as this is where quotations most often differ.
Which is cheaper: a steel or masonry hall?
A steel hall is cheaper than a masonry one: the median for a steel hall is 2,400 PLN/m², compared with 2,800 PLN/m² for a masonry hall at the enclosed shell stage. The sources used to calculate the medians consistently indicate that a masonry hall of a similar standard is noticeably more expensive, usually by a quarter or more.
However, like must be compared with like. The price of a steel hall usually includes the design, structure and sandwich-panel cladding with installation, but excludes foundations and industrial flooring. The price of a masonry hall generally covers the enclosed shell, including the load-bearing structure and enclosed building envelope, but excludes the design, installations and site development.
| Service | Median | Typically | Sources |
|---|---|---|---|
| Construction of a masonry hall | 2,800 PLN/m² | 2,800 ‑ 3,650 PLN/m² | 3 |
| Construction of a steel hall | 2,400 PLN/m² | 1,800 ‑ 2,550 PLN/m² | 3 |
Median and typical range from public price lists, as at 5 October 2026. Each price includes a source and quotation on the service page.
| Feature | Steel hall | Masonry hall |
|---|---|---|
| Typical price per m² | 1,800 ‑ 2,550 PLN/m² | 2,800 ‑ 3,650 PLN/m² |
| What the price usually includes | design, structure, cladding and installation | load-bearing structure to the enclosed shell stage |
| Construction time | several weeks from completion of the foundations | several months |
| Future extension | easy, by adding more frames | more difficult and expensive |
| Thermal and acoustic insulation | depends on sandwich-panel thickness | good, as masonry retains heat |
| Fire resistance | the structure requires fire protection | inherently high due to the material |
How much does a 500 m² hall cost?
Based on a contractor’s price-list example, a turnkey 500 m² steel hall costs about PLN 650,000, while the structure and cladding alone cost about PLN 1,200,000 at the median rate. A masonry hall of this size costs about PLN 1,400,000 at the median rate for an enclosed shell, typically PLN 1,400,000 ‑ 1,825,000.
Example costs for the hall structure alone (the median from public price lists multiplied by floor area):
| Floor area | Steel hall | Masonry hall (enclosed shell) |
|---|---|---|
| 100 m² | PLN 240,000 | PLN 280,000 |
| 300 m² | PLN 720,000 | PLN 840,000 |
| 400 m² | PLN 960,000 | PLN 1,120,000 |
| 500 m² | PLN 1,200,000 | PLN 1,400,000 |
| 1000 m² | PLN 2,400,000 | PLN 2,800,000 |
These figures are indicative, not a cost estimate. The price per m² falls for large warehouses and rises for small production halls, so a 1000 m² hall usually costs less than simple multiplication suggests, while a 100 m² hall costs more.
How much does it cost to build a 400 m² masonry hall?
At the median rate, a 400 m² masonry hall built to the enclosed shell stage costs about PLN 1,120,000, while half of quotations fall within PLN 1,120,000 ‑ 1,460,000. The most expensive sources quote rates of up to 5,500 PLN/m², but these are often gross prices or include a broader scope of work. The lowest rates, starting from 2,100 PLN/m², are usually net prices.
When comparing quotations, first check whether the price is net or gross. A business building a hall for commercial purposes can reclaim VAT, while a private individual building one for agricultural machinery or as a workshop cannot.
How much does it cost to build a sandwich-panel hall?
In practice, a sandwich-panel hall is a steel hall: a structure made from steel sections and clad with panels containing a mineral-wool or foam core. The typical cost is 1,800 ‑ 2,550 PLN/m², based on 3 sources collected by indekscen.pl. Thicker mineral-wool panels cost more but provide better insulation and fire resistance, which matters in a heated hall or production facility.
What does the price per m² of a hall exclude?
The price per m² of a hall excludes several major items that are listed separately in quotations or omitted entirely. The most common exclusions are:
- Building design and map. The design requires a site plan for design purposes, typically costing PLN 985 ‑ 1,050. We explain the formalities in the article planning permission: costs.
- Foundations and industrial flooring for a steel hall. The floor can be finished with resin: epoxy flooring installation usually costs 185 ‑ 300 PLN/m², including materials.
- Installations: electrical, heating and ventilation, as well as compressed air in many production halls.
- Site development: internal roads, manoeuvring areas, parking, fencing and utility connections.
- Supervision. A construction site manager charging per visit usually takes about PLN 425, while a fixed fee is agreed for larger projects.
- Equipment: sectional doors, overhead cranes, loading docks and rooflights.
Ground conditions can increase foundation costs by a substantial share of the enclosed-shell budget, so a geotechnical survey before the design stage is a sensible expense, not merely a formality.
What affects the cost of building a hall?
The cost of building a hall depends primarily on its structure (steel or masonry), floor area and height, followed by its intended use. A simple, unheated warehouse is the cheapest. A production hall with an overhead crane, heating, staff facilities and a mezzanine office can cost many times more per m².
- Height and span: a taller hall or a wider column-free span requires a heavier structure.
- Ground: poor ground conditions require deeper or piled foundations.
- Cladding standard: the thickness of the sandwich panels or the type of masonry and insulation.
- Location: access for heavy machinery, regional prices and the cost of the plot.
- Timing: masonry work slows down in winter, while a steel hall is less dependent on the weather.
When should you choose a masonry hall, and when a steel hall?
A steel hall is the better choice when time and budget matter and the building will serve as a warehouse, storage hall or simple production facility. It can easily be extended by adding more bays, and steel is simply cheaper than masonry for large spans.
A masonry hall makes sense when the building is intended to last for decades, will be heated, will combine hall space with an office or shop, or when fire resistance and acoustics are important, for example in a workshop with noisy machinery. Some investors choose a mixed solution: a steel structure with a masonry office and staff area.
How much does a plot for a hall cost?
The median price of industrial land in Poland is 116 PLN/m² (year-on-year change: +36.9%), based on transactions from the Property Price Register. Details and regional prices are available on the industrial land prices page. If you plan to build a hall on a building plot, check the local development plan or planning conditions, as not every plot permits commercial or industrial development.
How can you avoid overpaying for a hall?
- Compare quotations with the same scope: with or without foundations and flooring, net or gross, with or without the design.
- Ask for an estimate broken down by stage: structure, cladding, roof, doors, flooring and installations.
- Ask about the snow and wind loads used in the design. An overly light structure is cheaper, but may not meet the standards for your zone.
- Check the contractor’s completed projects and ask about the warranty for the structure and cladding.
„Średni koszt budowy hali murowanej o powierzchni 400 m² wynosi od 3 500 do 5 500 zł/m² brutto”
Carcon.pl, source
„Budowa hali murowanej kosztuje od 2 100 zł do 3 400 zł netto za m² w stanie surowym zamkniętym.”
CoBouw.pl, source
„hale murowane – od 2400 do 3200 zł/m²”
Stalomat.pl, source
You can find more construction prices in the house construction category and the article cost of building a house, as well as details of both construction methods on the construction of a masonry hall and construction of a steel hall pages.
The prices in this article come from public contractors’ price lists and trade publications, updated: 5 October 2026. Each price on the service page includes its source, date and a verbatim quotation.
Frequently asked questions
How much does it cost to build a 100 m² hall?
Mała hala murowana 100 m² w stanie surowym zamkniętym kosztuje przy medianie około PLN 280,000, a stalowa około PLN 240,000. Przy małych halach stawka za m² bywa wyższa niż przy dużych, bo koszty projektu, dźwigu i dojazdu rozkładają się na mniej metrów.
How much does a 300 m² hall cost?
Hala stalowa 300 m² to przy medianie około PLN 720,000 (typowo PLN 540,000 ‑ 765,000), a murowana w stanie surowym zamkniętym około PLN 840,000. Fundamenty, posadzka i instalacje dochodzą osobno.
How much does the steel frame of a hall cost?
Najtańsze oferty na konstrukcję stalową z obudową i montażem zaczynają się od 790 PLN/m², ale to zwykle duże, proste hale magazynowe bez fundamentów i posadzki. Typowy przedział dla hali stalowej to 1,800 ‑ 2,550 PLN/m².
Can a hall of up to 300 m² be built without planning permission?
Hala magazynowa lub produkcyjna co do zasady wymaga pozwolenia na budowę, a zwolnienia dotyczą wąskich przypadków, na przykład niektórych budynków rolniczych. Zanim kupisz konstrukcję, zapytaj architekta albo wydział architektury w starostwie, jaka procedura obowiązuje na Twojej działce.
How long does it take to build a steel hall and a masonry hall?
Hala stalowa powstaje zwykle w kilka tygodni od wylania fundamentów, bo elementy są prefabrykowane i skręcane na miejscu. Hala murowana trwa kilka miesięcy, bo mury i wieńce potrzebują czasu, a prace mokre zależą od pogody.
Check prices with sources
Every amount quoted in the article has a source, date and verbatim quote from the price list on the service page.
Translation of the original Polish article dated 30 September 2026. Quotations from price lists are in Polish, as published by the companies. Read the original in Polish.
Found an error? Report it. Do you provide these services? Add your company's price list free of charge.